disabled persons watching eclipse

Ensuring Your Future

Envisioning the future

Find out about WAC Plans for 2024

Over the last several years, we have been looking for a solution for our current Community Day Services location, which has outlived its useful life, and has an ever-growing list of repairs and maintenance issues. It is safe, but desperately outdated.

Our hard work paid off, and the perfect solution did appear.

Last summer, Warren Achievement Center acquired a building on the Northwest side of Monmouth. This 10,000 square foot facility, which sits on nearly half of a city block, will be the future Community Day Services location – securing the next 50 years of service. This project is one of the largest in the proud history of Warren Achievement Center.

Our talented maintenance staff have been renovating the building and have framed in classrooms, offices, and more. The new Community Day Services location will include large spaces for all levels of disability, offices, meeting rooms, storage, a large kitchen, cafeteria, open space, and plenty of area outside for activities and parking.

In addition, we will be building a 4400 square foot addition, which will resemble a medical facility. The project is costly, but not unrealistic. Our generous community has allowed us to continue moving forward with the project. The fundraising will continue, as community support is of vital importance. You may wish to donate to the project.

We have been working with a local architectural firm, and things have been going well. Please enjoy the renderings for the project, which reflect the existing building, as well as the addition.

See Our New Building

Follow Our Progress!

Bid Placed

Bid placed on VFW building in Northwest Monmouth.

December 14, 2022

Bid Accepted

Bid Accepted by the VFW.

December 15, 2022

WAC Takes Possesion

Warren Achievement Center officially takes possession of the VFW building to be the new Community Day Services facility.

July 26, 2023

Architects Hired

Hired local architectural firm Klingner & Associates for design work and project management.

October 2023

Clearing Begins

Warren Achievement Center maintenance staff begins to clear building.

August 1, 2023

Rooms Framed

Maintenance staff began framing in classrooms, offices, and other rooms.

November 2023

Electrical Work Begins

Electrical work begins.

March 2024

Walls Prepped

Prepared and primed interior walls.

March 2024

Floor Plan Design Approved

Final floorplan design for 4400 square foot addition approved.

June 2024

Interior Painted

Interior painting completed.

August 2024

Structural Work to Begin

Finishing work on original structure begins.

August 2024

Structural Work To Be Complete

Work to conclude on original structure.

December 2024

Partial Transfer of Services

Partial transfer of services to new Community Day Services facility.

Spring 2025

Construction of Addition Begins

Work on building addition to begin.

Summer 2025

Addition Construction to be Completed

Work to be completed on building addition.

Winter 2025

Final Transfer of Services

Final transfer of services to new Community Day Services facility.

Winter 2025